HEMPSTEAD ISD BOND UPDATES

BOND NEWS - April 2026

Thank you for your continued support in making these district improvements possible. Stay connected for more updates as bond projects move forward across the district. 

 
 

Construction Timeline

The projects covered by the 2024 bond referendum will be undertaken from 2024 through completion. Some factors that impact the schedule are:

  • how imminently critical the need;
  • the volume and complexity of projects that can be effectively managed simultaneously;
  • economies of scale that can be achieved by bundling similar projects when doing so maximizes resources and is practical;
  • minimize interruptions to the campus environment.

*Please note that all designs/renderings are subject to change. 

 

Hempstead Early Childhood Center

  • Construction is ongoing
  • Grading site for paving completed
  • Ongoing site grading
  • Scheduling cement stabilization
  • Gas line installation is complete
  • Structural Steel is being erected
  • Site Pole bases have been poured.
  • Transformer and Mechanical Yard slabs have been poured.
 

Hempstead Middle School

  • Construction ongoing 
  • Demolition complete
  • Temporary wall built
  • Ongoing building pad work
  • Started drilling piers
  • Working on underground utilities
 

Hempstead High School 

  • Demo 80% complete
  • Excavated building pad
  • Ongoing building pad work
  • Installation of manholes on the new cafeteria and band hall sites
  • Ongoing Utility Work
 

Bobcat Stadium 

 
 

Athletics:

  • Track and Field
    • The project is 100% complete.
    • Installation of the fence wrapping has now been completed, enhancing the overall appearance of the facility.
  • Baseball Concession Stand & Restrooms
    • Baseball Concession Stand and Restroom - Summer 2026
 

Additional Updates

Hempstead ES

  • Tellepsen is working on GMP

District Improvements

  • HVAC Scope
    • Tellepsen is currently pricing the 95% Construction Documents set.
  • HMS Roofing
    • Summer 2026
 

About Bond 2024

On May 4, 2024, voters approved a $45.7 million bond referendum to build a new Early Childhood Center, address aging facilities, and update safety and infrastructure.

Safety, Security and Functionality
Proposition A will provide a replacement campus for Hempstead Early Childhood Center, a cafeteria and band hall addition at Hempstead High School, an auxiliary gym addition at Hempstead Middle School, an enclosed connector from the cafeteria/band hall to Hempstead Middle School and between all four buildings at Hempstead Elementary School, concession/restroom building at baseball field, HVAC unit replacements, control upgrades, testing & balance districtwide, and a roof replacement at Hempstead Middle School at a cost of $42,320,000.

Proposition B will provide a new synthetic turf field and track at Bobcat Stadium at a cost of $3,400,000.

 
 
Library

Our Long-Range Facility Plan

The Hempstead ISD Board of Trustees adopted the Long-Range Facility Plan at the November 13, 2023 school board meeting.

Read More
 
 

Do you have questions about Bond 2024 progress Submit a Question.